Arrival of RTG cranes marks latest step in expansion programme that includes 300-metre berth extension and enhanced reefer facilities

RTG cranes Mindanao ITCSI 2026

Image: ITCSI

Mindanao Container Terminal (MCT), the International Container Terminal Services (ICTSI) operation supporting Northern Mindanao trade, is ramping up capacity to accommodate rising cargo demand and additional shipping services.

ICTSI said the arrival of four hybrid rubber-tired gantry (RTG) cranes marks the latest step in an expansion programme that includes a 300-metre berth extension, orders of three post-Panamax quay cranes, expanded reefer facilities, and additional container storage capacity.

“We formalised the project in late 2024 and established a clear timetable,” said Aurelio Garcia, MCT’s chief executive officer.

”I’m pleased to say that everything remains on schedule. The RTGs arrived roughly three months ahead of schedule, marking an important step in the terminal’s expansion.”

Construction of the berth extension is progressing, with the first 120 metres targeted for completion by the end of the first quarter of 2027.

The first of three new post-Panamax quay cranes is expected to arrive shortly afterward and will become operational following commissioning, the group continued.

Once completed, the initial phase will increase MCT’s operational berth length to 420 metres, providing additional capacity for vessel calls and shipping services.

The expansion also includes additional infrastructure to support growing operations.

MCT is expanding its reefer facilities to accommodate increasing volumes of refrigerated import and export cargo, while work is underway to expand the empty container depot and increase container storage capacity.

Supporting infrastructure projects includes the construction of a new electrical substation that will provide the power required for additional equipment and future operational needs.

Located within the Phividec Industrial Estate, MCT serves as Northern Mindanao’s primary international container gateway.

The terminal supports the movement of import and export cargoes and helps connect businesses across the region with domestic and international markets.

Garcia said the arrival of the new RTGs highlights the progress being made across MCT’s expansion programme. 

“While we’ve seen construction progress over the past several months, seeing the first RTG arrive and be discharged was a significant moment for the project,” he outlined.

”It reflects the progress being made across the terminal and the work that continues behind the scenes.”

The current phase forms part of MCT’s long-term expansion programme, which is scheduled for completion in the first quarter of 2028.

By then, MCT is expected to complete the full 300-metre berth extension and commission all three quay cranes.

“With additional berth capacity becoming available next year, we expect to be in a stronger position to accommodate more vessel calls and support additional shipping services,” Garcia added.

“We look forward to completing the programme on schedule and continuing to build on MCT’s role in supporting trade and industry in Mindanao.”